| Number of remarks |
The total number of remarks found in a given time period/phase/test
type. A remark is a claim made by test engineer that the application
shows an undesired behavior. It may or may not result in software
modification or changes to documentation. |
One of the earliest indicators to measure once the testing
commences; provides initial indications about the stability of the
software. |
Total number of remarks found. |
| Number of defects |
The total number of remarks found in a given time period/phase/test
type that resulted in software or documentation modifications. |
A more meaningful way of assessing the stability and reliability of
the software than number of remarks. Duplicate remarks have been
eliminated; rejected remarks have been done. |
Only remarks that resulted in modifying the software or the
documentation are counted. |
| Remark status |
The status of the defect could vary depending upon the
defect-tracking tool that is used. Broadly, the following statuses are
available: To be solved: Logged by the test engineers and waiting to be
taken over by the software engineer. To be retested: Solved by the
developer, and waiting to be retested by the test engineer. Closed: The
issue was retested by the test engineer and was approved. |
Track the progress with respect to entering, solving and retesting
the remarks. During this phase, the information is useful to know the
number of remarks logged, solved, waiting to be resolved and retested. |
This information can normally be obtained directly from the defect
tracking system based on the remark status. |
| Defect severity |
The severity level of a defect indicates the potential business
impact for the end user (business impact = effect on the end user x
frequency of occurrence). |
Provides indications about the quality of the product under test.
High-severity defects means low product quality, and vice versa. At the
end of this phase, this information is useful to make the release
decision based on the number of defects and their severity levels. |
Every defect has severity levels attached to it. Broadly, these are
Critical, Serious, Medium and Low. |
| Defect severity index |
An index representing the average of the severity of the defects. |
Provides a direct measurement of the quality of the
product—specifically, reliability, fault tolerance and stability. |
Two measures are required to compute the defect severity index. A
number is assigned against each severity level: 4 (Critical), 3
(Serious), 2 (Medium), 1 (Low). Multiply each remark by its severity
level number and add the totals; divide this by the total number of
defects to determine the defect severity index. |
| Time to find a defect |
The effort required to find a defect. |
Shows how fast the defects are being found. This metric indicates
the correlation between the test effort and the number of defects found. |
Divide the cumulative hours spent on test execution and logging
defects by the number of defects entered during the same period. |
| Time to solve a defect |
Effort required to resolve a defect (diagnosis and correction). |
Provides an indication of the maintainability of the product and can
be used to estimate projected maintenance costs. |
Divide the number of hours spent on diagnosis and correction by the
number of defects resolved during the same period. |
| Test coverage |
Defined as the extent to which testing covers the product’s complete
functionality. |
This metric is an indication of the completeness of the testing. It
does not indicate anything about the effectiveness of the testing. This
can be used as a criterion to stop testing. |
Coverage could be with respect to requirements, functional topic
list, business flows, use cases, etc. It can be calculated based on the
number of items that were covered vs. the total number of items. |
| Test case effectiveness |
The extent to which test cases are able to find defects. |
This metric provides an indication of the effectiveness of the test
cases and the stability of the software. |
Ratio of the number of test cases that resulted in logging remarks
vs. the total number of test cases. |
| Defects/ KLOC |
The number of defects per 1,000 lines of code. |
This metric indicates the quality of the product under test. It can
be used as a basis for estimating defects to be addressed in the next
phase or the next version. |
Ratio of the number of defects found vs. the total number of lines
of code (thousands) |
| PROJECT |
| Workload capacity ratio |
Ratio of the planned workload and the gross capacity for the total
test project or phase. |
This metric helps in detecting issues related to estimation and
planning. It serves as an input for estimating similar projects as well. |
Computation of this metric often happens in the beginning of the
phase or project. Workload is determined by multiplying the number of
tasks against their norm times. Gross capacity is nothing but planned
working time, determined by workload divided by gross capacity. |
| Test planning performance |
The planned value related to the actual value. |
Shows how well estimation was done. |
The ratio of the actual effort spent to the planned effort. |
| Test effort percentage |
Test effort is the amount of work spent, in hours or days or weeks.
Overall project effort is divided among multiple phases of the project:
requirements, design, coding, testing and such. |
The effort spent in testing, in relation to the effort spent in the
development activities, will give us an indication of the level of
investment in testing. This information can also be used to estimate
similar projects in the future. |
This metric can be computed by dividing the overall test effort by
the total project effort. |
| Defect category |
An attribute of the defect in relation to the quality attributes of
the product. Quality attributes of a product include functionality,
usability, documentation, performance, installation and
internationalization. |
This metric can provide insight into the different quality
attributes of the product. |
This metric can be computed by dividing the defects that belong to a
particular category by the total number of defects. |
| PROCESS |
| Should be found in which phase |
An attribute of the defect, indicating in which phase the remark
should have been found. |
Are we able to find the right defects in the right phase as
described in the test strategy? Indicates the percentage of defects that
are getting migrated into subsequent test phases. |
Computation of this metric is done by calculating the number of
defects that should have been found in previous test phases. |
| Residual defect density |
An estimate of the number of defects that may have been unresolved
in the product phase. |
The goal is to achieve a defect level that is acceptable to the
clients. We remove defects in each of the test phases so that few will
remain. |
This is a tricky issue. Released products have a basis for
estimation. For new versions, industry standards, coupled with project
specifics, form the basis for estimation. |
| Defect remark ratio |
Ratio of the number of remarks that resulted in software
modification vs. the total number of remarks. |
Provides an indication of the level of understanding between the
test engineers and the software engineers about the product, as well as
an indirect indication of test effectiveness. |
The number of remarks that resulted in software modification vs. the
total number of logged remarks. Valid for each test type, during and at
the end of test phases. |
| Valid remark ratio |
Percentage of valid remarks during a certain period. Valid remarks =
number of defects + duplicate remarks + number of remarks that will be
resolved in the next phase or release. |
Indicates the efficiency of the test process. |
Ratio of the total number of remarks that are valid to the total
number of remarks found. |
| Bad fix ratio |
Percentage of the number of resolved remarks that resulted in
creating new defects while resolving existing ones. |
Indicates the effectiveness of the defect-resolution process, plus
indirect indications as to the maintainability of the software. |
Ratio of the total number of bad fixes to the total number of
resolved defects. This can be calculated per test type, test phase or
time period. |
| Defect removal efficiency |
The number of defects that are removed per time unit
(hours/days/weeks) |
Indicates the efficiency of defect removal methods, as well as
indirect measurement of the quality of the product. |
Computed by dividing the effort required for defect detection,
defect resolution time and retesting time by the number of remarks. This
is calculated per test type, during and across test phases. |
| Phase yield |
Defined as the number of defects found during the phase of the
development life cycle vs. the estimated number of defects at the start
of the phase. |
Shows the effectiveness of the defect removal. Provides a direct
measurement of product quality; can be used to determine the estimated
number of defects for the next phase. |
Ratio of the number of defects found by the total number of
estimated defects. This can be used during a phase and also at the end
of the phase. |
| Backlog development |
The number of remarks that are yet to be resolved by the development
team. |
Indicates how well the software engineers are coping with the
testing efforts. |
The number of remarks that remain to be resolved. |
| Backlog testing |
The number of resolved remarks that are yet to be retested by the
development team. |
Indicates how well the test engineers are coping with the
development efforts. |
The number of remarks that have been resolved. |
| Scope changes |
The number of changes that were made to the test scope. |
Indicates requirements stability or volatility, as well as process
stability. |
Ratio of the number of changed items in the test scope to the total
number of items. |